Project Timeline

Estimated Time for Installation Completion (2-6 Weeks)


  • Purchase Agreement is Signed

  • First Payment is Made

  • Equipment is Ordered & Permit Package Started

  • Delivery Driver Will Contact You for Appointment, Generally a 2 Hour Window

  • NOC is Filed With The Clerk Of Court

  • Permit Application is Submitted to the City/County

  • Materials Arrive Onsite, 2nd Payment is Due

  • As Soon as the Permit is Issued, the Installation is Scheduled

  • A High Quality Installation is Completed, System is Tested, City/County Inspection Performed

  • After Passing City/County Inspection, Final Payment Due

  • Interconnection Application is Submitted to the Utility Company

  • Utility Processes Application (Usually 7 - 30 Days)

  • Permission to Operate is Granted

  • Utility Inspection Performed

  • Bi Directional Meter Installed

  • Congratulations!! - Turn On Your New PV System!

System Warranties


Modules - 25 Year Linear Power Output - (Manufacturer)
Inverters - 25 Years - Enphase (Manufacturer)
Racking - 25 Years - (Manufacturer)
Installation - 10 Years Parts & Labor Against Installation Defects (FPS)

Additional Notes


Purchase Agreement


Initializing Database...

Preparing Purchase Agreement...

Preparing Presentation...

Payment Schedule

System Total = $

Prompt payments by check or wire transfer helps us complete your project on time.


$

$

$